Project showcases innovative concrete construction, on-time delivery and a major milestone in improving mobility between Phoenix and Casa Grande.
Pulice – a FlatironDragados company has completed the Arizona Department of Transportation's I-10 Bridges over the Gila River project in Pinal County, Arizona, delivering the first completed segment of the larger I-10 Wild Horse Pass Corridor Project between Phoenix and Casa Grande.
The project replaced two aging bridges dating to 1964 with new, wider and higher structures featuring three lanes in each direction, full-width shoulders and deeper foundations designed to improve long-term resilience. Construction began in May 2024.
"Congratulations to ADOT and the greater community. This project was a significant success. Our team delivered it on time, safely and without major disruptions to traffic," says Victor Jimenez, President of Pulice.
Innovation and Safety Drive Construction at the I-10 Wild Horse Pass Corridor Project
Beyond replacing critical infrastructure, the project showcased Pulice's ability to apply innovative engineering and construction methods while maintaining traffic along a busy interstate corridor.
One notable achievement came when the project team completed Arizona's first bridge deck concrete pour combining macrofibers and microfibers. The innovative concrete mix helps control cracking and improve long-term durability, supporting the performance and longevity of the new bridges.
Pulice also worked closely with ADOT and the Gila River Indian Community to implement an innovative construction sequence that allowed crews to build the new bridges in phases while maintaining interstate traffic. This approach reduced construction safety risks and minimized disruptions for motorists throughout the project.
"Successful projects depend on strong partnerships and open communication," says Reza Kamalizad, Pulice senior project manager. "We valued the opportunity to work closely with the Gila River Indian Community, listen to its priorities and find solutions together."
The completed bridges represent the first of four segments in ADOT's I-10 Wild Horse Pass Corridor Project. Once crews complete the remaining segments, scheduled for late 2029, the corridor will provide three travel lanes in each direction, improving mobility and supporting continued growth between Phoenix and Casa Grande, Arizona.
For Pulice, the milestone reflects the expertise, collaboration and commitment to Safety Above All that drives successful infrastructure delivery.