Milestone advances ADOT’s Loop 303 widening project in north Phoenix near TSMC Arizona, where crews placed 18 girders on future bridge.
Pulice – a FlatironDragados company set the first girders on the Arizona Department of Transportation’s SR 303L and I-17 Traffic Interchange project, marking a major bridge milestone for one of north Phoenix’s most important mobility investments.
“Setting the first girders is a major milestone because it shows the bridge work moving from foundations into visible structure,” said Field Engineer Cheryl Gurmelle. “This operation took close coordination between our crews, operators and ADOT, especially with night work and girders of this size. Seeing the first 18 girders set safely is a strong step forward for the project.”
The first girder set included:
- 18 girders placed on future bridge RAMP SW, which will run over the existing southbound frontage road.
- Girder placement across spans 1, 2 and 3
- About 135-foot girders set on span 2 Friday night
- About 103-foot girders set on spans 1 and 3 Thursday and Saturday nights
RAMP SW is one of five bridges planned for the $129 million project. The structure was a logical first bridge for girder placement because its location will make it easier to open to traffic once complete.
The project will create direct freeway-to-freeway ramps at SR 303L and I-17, where drivers currently must leave the highway and pass through a traffic signal. The work also will widen SR 303L between 51st Avenue and I-17 from two to three lanes in each direction and build major drainage, retaining walls and sound walls.
Once complate, the new infrastructure will improve safety and mobility in a fast-growing north Phoenix corridor near the massive TSMC Arizona facility. Construction is expected to finish in 2028.