The Challenge

The project included removal of existing asphalt and concrete pavement, lighting, and utility vaults; construction of new PCCP on the taxiway; approach and anchor slabs for both eastbound and westbound bridges over Sky Harbor Boulevard; asphaltic concrete for shoulders, infield areas, and access road; lighting, and utility vaults.

The federally-funded project included fast-track construction (60-day closure), and coordination with airside operations. During preconstruction services, Pulice provided constructability reviews, cost models, CPM schedules, subcontract bid packages, and the GMP.

Sky Harbor International Airport, Taxiway "R" CMAR