San Vicente Marina

Construction of a new marina at San Diego’s most used recreational reservoir, San Vicente.  The Marina is the fourth phase of five projects at the reservoir and is part of the San Diego County Water Authority’s Emergency Storage Project.

The project included roughly 650,000 CY of excavation/fill, lining the entire marina with approximately 60,000 tons of rip rap, 2,200 LF of 48” RCPP, construction of a 114 foot wide by 900 foot long boat ramp, new concession, comfort, & office buildings, two small pump stations, and a new parking lot with landscaped medians.

AWARD WINNER

2016 APWA Project of the Year (San Diego Chapter) and 2016 Award of Excellence by the United States Society on Dams.

 

Owner: San Diego Water Authority
Location: Lakeside, CA
Construction Cost: $22.7M
Market: Water