The Challenge

Widening of McQueen Road from two to six lanes between Queen Creek Road and Ocotillo Road, including the replacement and widening of two box culvert crossings in the Consolidated Canal.

Pulice provided preconstruction services, which included cost models, project planning and CPM scheduling for design and construction, alternative systems evaluation and constructability reviews at various levels of design, utility coordination, subcontractor bid packages, and submitted a GMP proposal for review and negotiation.

The team accomplished a 20-day fast-track removal and replacement of a Consolidated Canal cast-in-place box culvert (2,600 cy concrete and 775,000 lbs. rebar) to accommodate the annual dry-up.

McQueen Road Improvements, Queen Creek Rd. to Riggs Road