The Challenge

The developer, Blueridge Transportation Group (BTG), led by ACS Infrastructure Development, is under contract to build the 10.3-mile toll road in Harris County, Texas, and is responsible for financing, designing, and reconstructing the project along with the operation and maintenance of the corridor for a total of 52 years. The four-lane toll road will connect southern Harris County to the Texas Medical Center in downtown Houston, with eight direct connectors.

Major scope includes 10 miles of concrete pavement and 54 bridges all completed in 1,000 days. The design-build joint venture is led by Dragados USA and Pulice.

10

Miles

Approximately 10.3 miles of concrete pavement.

54

Bridges Complete

Includes 36 Various bridges over roadways, railroad and bayous.

1,000

Days of Work

Finished project in contract time without delays.